Fitzroy House owners expected to move in September this year
Fitzroy House Construction Update – April 2021
Since our last Fitzroy House construction update a milestone was reached with the removal of the crane, the building is now at lock-up stage.
Lifts have been installed and finishing trades are systematically working their way up the building, plastering is now complete on all levels and the install of joinery, floor and wall finishes is well underway.
We look forward to completing construction and handing the keys over to Fitzroy House homeowners in September 2021.